BD Green Pier- Piers
Showing posts with label
MP 2 Log
.
Show all posts
Showing posts with label
MP 2 Log
.
Show all posts
January 13, 2012
Log 27
Log Date: January 13, 2012
Marking Period 2
Green Pier
Work Started
STEMM Midterm
Work Completed
Formal Progress Update Outline
Reminders
STEMM midterm done by mid-year
Put together AutoCAD drawings
January 06, 2012
Log 26
Log Date: January 6, 2012
Marking Period 2
Green Pier
Work Started
Formal Progress Update Outline
STEMM Midterm
Work Completed
STEMM Midterm Manufacturing
Reminders
STEMM midterm done by mid-year
Put together AutoCAD drawings
January 04, 2012
Log 25
Log Date: January 4, 2012
Marking Period 2
Green Pier
Work Started
STEMM Midterm
Work Completed
Hardware lists configured
Reminders
STEMM midterm done by mid-year
Put together AutoCAD drawings
December 23, 2011
Log 24
Log Date: December 23, 2011
Marking Period 2
Green Pier
Work Started
STEMM Midterm Assignment
Work Completed
Pictures for the introduction to STEMM Midterm
AutoCAD screenshots
Material lists formatted and printed
Reminders
STEMM midterm done by mid-year
Put together AutoCAD drawings
December 21, 2011
Log 23
Log Date: December 21, 2011
Marking Period 2
Green Pier
Work Started
STEMM Midterm Assignment
Work Completed
Added pictures to midterm assignment
Added engineering and manufacturing types to midterm assignment
Reminders
STEMM midterm done by mid-year
December 16, 2011
Log 22
Log Date: December 16, 2011
Marking Period 2
Green Pier
Work Started
STEMM Midterm Assignment
Work Completed
First section midterm assignment
Reminders
STEMM midterm done by mid-year
December 14, 2011
Log 21
Log Date: December 14, 2011
Marking Period 2
Green Pier
Work Started
STEMM Midterm Assignment
Work Completed
Hardware list
Press Release
Reminders
Need cut out view from AutoCAD drawing
December 09, 2011
Log 20
Log Date: December 7, 2011
Marking Period 2
Green Pier
Work Started
Press Release
Dock hardware material list
Work Completed
Nails, corner brackets, etc. calculated for material list
Reminders
Press Release due Dec. 12
Need cut out view from AutoCAD drawing
December 07, 2011
Log 19
Log Date: December 7, 2011
Marking Period 2
Green Pier
Work Started
Press Release
Work Completed
Finished detailed AutoCAD drawing
Reminders
Press Release due Dec. 12
Need cut out view from AutoCAD drawing
December 02, 2011
Log 18
Log Date: December 2, 2011
Marking Period 2
Green Pier
Work Started
Continued updates of AutoCAD drawing
Work Completed
Material list completed
Added railing posts
Balusters finished
Reminders
AutoCAD drawing needs to be updated to be more specific
Press Release due Dec. 12
November 23, 2011
Log 17
Log Date: November 23, 2011
Marking Period 2
Green Pier
Work Started
Continued updates of AutoCAD drawing
Work Completed
Added joists
Support structures added
Caps for support structures designed
Reminders
AutoCAD drawing needs to be updated to be more specific
Need complete material list to start realistic model
Press Release due Dec. 12
November 18, 2011
Log 16
Log Date: November 18, 2011
Marking Period 2
Green Pier
Work Started
Began work on STEMM midterm
Started Press Release document
Continued to update AutoCAD drawing
Work Completed
Received calendar updates and due dates
Reminders
AutoCAD drawing needs to be updated to be more specific
Need complete material list to start realistic model
Press Release due Dec. 12
November 16, 2011
Log 15
Log Date: November 16, 2011
Marking Period 2
Green Pier
Work Started
Calculations of nails, bolts, etc. needed for piers
Work Completed
Basic material list finished
Reminders
AutoCAD drawing needs to be updated to be more specific
Need complete material list to start realistic model
November 08, 2011
Log 14
Log Date: November 9, 2011
Marking Period 2
Green Pier
Work Started
Edited AutoCAD model
Began additions of details
Started compiling materials list
Work Completed
Formal Progress Update presented
Reminders
Need to get work started on model
Older Posts
Home
Subscribe to:
Posts (Atom)